You Won a Big Contract: How to Fund the Gap Before the First Payment Arrives

Taking the $300,000 contract puts $66,000 of margin on the table, but the job's cash drops to -$103,500 by the end of month 2 and stays below zero until month 7. Turning it down keeps the cash safe and gives up the margin. Whether to take it depends on whether you can find $103,500 before the first payment comes in.

Month Cash out Cash in (net of retainage) Running cash
1 $60,000 $0 -$60,000
2 $43,500 $0 -$103,500
3 $43,500 $54,000 -$93,000
4 $43,500 $54,000 -$82,500
5 $43,500 $54,000 -$72,000
6 $0 $54,000 -$18,000
7 $0 $54,000 +$36,000
8 $0 $30,000 +$66,000
Total $234,000 $300,000 $66,000 margin

The number to fund is the lowest point on the running cash line, -$103,500, because the $66,000 of margin only shows up months after the money has gone out.

Chart: running cash position by month. It falls to -$103,500 at the end of month 2, stays below zero until month 7, and ends $66,000 above zero when the retainage is released. A dashed line shows the shallower path with a 10 percent deposit.

This contract and its numbers are made up to show the arithmetic. The inputs and their basis are under "How this example is built" at the end.

What shrinks the gap

Change, one at a time Low point Change
As modelled -$103,500 none
10 percent deposit ($30,000) paid before work starts, credited against the invoices -$73,500 +$30,000
Net-30 instead of net-45 (the +$43,500 is an upper bound on the improvement: net-45 is rounded up to 2 months, net-30 is exactly 1) -$60,000 +$43,500
Invoice twice a month -$103,500 $0

A change helps only if it moves cash in before the low point. Twice-monthly invoicing does not here: the first payment still lands after month 2's costs. The deposit is a contract term paid before work starts, so it has to be asked for before signing.

What late payment does

Payments arrive Low point Still to find after $40,000 in the bank
As modelled -$103,500 $63,500
30 days later -$147,000 $107,000
60 days later -$190,500 $150,500

Each month of delay moves the low point later and deeper. The cash balance is in the inputs table; payroll and overhead the business already carries come on top.

What borrowing the gap costs

Interest of about $2,000 to $4,300 against $66,000 of margin is small, so the decision turns on whether the cash can be had and on late payment, not on the rate.

Deposit Annual rate Cash to find Interest Share of contract Margin left
None 8 percent $103,500 $2,860 1.0 percent $63,140
None 10 percent $103,500 $3,575 1.2 percent $62,425
None 12 percent $103,500 $4,290 1.4 percent $61,710
$30,000 8 percent $73,500 $2,060 0.7 percent $63,940
$30,000 10 percent $73,500 $2,575 0.9 percent $63,425
$30,000 12 percent $73,500 $3,090 1.0 percent $62,910
Line of credit sized to Amount Against the low point of $103,500
Month 1's costs $60,000 Used up in month 2, $43,500 short, with three months of work to go
The low point exactly $103,500 Enough only if no payment slips
The low point plus a 20 percent buffer $124,200 $20,700 spare, less than the $43,500 that a 30-days-late payment adds
The 30-days-late low point $147,000 Covers the late case with nothing spare

Swap in the rates the bank offers and the buffer you would want. The interest basis is in the inputs table.

When the other choice is right

Take it as written when Decline or reprice when
Cash plus a line the bank has approved covers the low point, including the 60-days-late row No combination of deposit, terms and credit covers the low point
The contract charges the customer for paying late Late payment costs the customer nothing, so the 30 and 60 day rows are the likely case
The customer is a small share of revenue The customer is a large share: $300,000 is 25 percent of an example $1,200,000 business
Job-level costs are current enough to forecast from The books are months behind, so no forecast can be built

Before signing

  • Tax: the figures are before tax. Ask the accountant how much of the interest reduces taxable profit and when the margin is taxed, then compare taking and declining after tax.
  • Contract terms: retainage, deposits and late-payment rights differ by state and contract. Ask a business attorney to read them.
  • Who does what: a controller builds the weekly cash forecast, the banker sizes the line, and the attorney reads the payment terms.

Before you say yes to a job this size, get the month-by-month cash line and size your commitment by its lowest point. Here that is $103,500, well past the $60,000 the first month costs.

To test a contract with its own numbers, use the contract affordability calculator. If it is unclear whether the problem is timing, margin or books, the profit-cash diagnostic takes about three minutes. For a 1:1 review, email [email protected] with the contract value, payment terms, current cash and credit line.

How this example is built

Input Value Basis
Contract $300,000 Five months of work
Direct costs $234,000, 78 percent of the contract $60,000 in month 1, $43,500 in each of months 2 to 5
Margin $66,000 Contract minus direct costs, before the business's own overhead
Invoices $60,000 at each month end Five equal invoices, months 1 to 5
Retainage 10 percent of each invoice, $30,000 in all Held back by the customer, released at the end of month 8
Payment time 45 days Modelled as the end of the second month after the invoice (the cautious round-up)
Deposit $30,000, 10 percent of the contract Paid before work starts, credited evenly against the five invoices
Cash already in the bank $40,000 For this contract alone
Size of the business $1,200,000 of revenue For the share-of-revenue row
Borrowing Interest at 8, 10 and 12 percent a year Rates to compare; charged on the average balance drawn over months 1 to 6